SoftBank’s US$3.73 billion hit on power equipment fits in four paragraphs on page five of its financial report for the six months to Sept. 30. The numbers in those paragraphs say more than the headline loss does.
The company behind the charge is Silver Bands 7 LLC, which the report calls SB7, a subsidiary funded by SoftBank Group and its second Vision Fund. Its job was to lock down “power generation-related equipment to secure robust power supply infrastructure for AI data center projects in the U.S., including the PORTS-Pike Technology Campus in Pike County, Ohio.” It did that through manufacturing-capacity reservations, equipment purchase contracts and other agreements.
Then the plan changed. “SB7 revised its equipment procurement strategy given the evolving requirements of its existing and planned projects,” the report says.
The arithmetic of a change of plan
The report gives SB7’s cumulative payments for this equipment, from the last fiscal year through Sept. 30, as ¥1,500,886 million, or US$9.48 billion. The loss it booked is ¥597,248 million, or US$3.73 billion.
Divide one by the other: about 39% of everything SB7 had paid for power equipment is now written off. That’s our calculation, not SoftBank’s, and it treats the whole loss as a share of payments made. The report’s breakdown makes that a fair, if rough, comparison.
That breakdown has two parts. ¥457,030 million (US$2.85 billion) is “non-refundable advance payments made to secure manufacturing capacity and purchase equipment.” That’s 77% of the charge, money handed to suppliers to hold factory slots. The other ¥140,218 million (US$0.88 billion), or 23%, covers “contract modifications and settlements.” The report doesn’t name the suppliers.
The figures also imply the rate SoftBank used: about ¥160 to the US dollar.
The US$2.1 billion that isn’t on the books
There’s a partial offset, and SoftBank chose not to count it. SB7 “became entitled to receive rebates of up to $2.1 billion over the next 10 years on future equipment purchases, subject to certain conditions,” the report says. Because the amount “could not be determined as of September 30, 2026,” the company didn’t record those rebate rights as an asset.
Read the condition again: rebates on future purchases. SB7 gets the money back only if it keeps buying from the same suppliers for a decade. A company that just revised its strategy is promising to keep buying.
Where it lands in the results
The charge sits in “Other gain (loss)” and helps explain why SoftBank Group reported a net loss attributable to owners of ¥768,007 million for the six months. Reuters, via The Star, put the July–September quarter alone at a ¥1.1 trillion (about US$7 billion) net loss, against a ¥2.5 trillion profit a year earlier. Reuters also quoted CFO Yoshimitsu Goto: “There are many cases where you have to change strategy for what you thought would probably have been OK a year or two ago.”
The page-five paragraphs don’t mention OpenAI. Reporting on the Pike County campus, including Open magazine’s explainer, describes OpenAI as its main tenant, with capacity coming online in phases from 2028.
That matters for anyone counting gigawatts. Power equipment has been one of the tightest bottlenecks in the AI build-out, and buyers have paid up front to get in line. SB7 paid US$9.48 billion to be in that line. It’s now leaving with a 39% loss on the ticket and a promise of up to US$2.1 billion if it comes back.
Jeff Cameron writes about the business and policy side of AI for prompt/power. A chief operating officer by trade, he also writes for Not An Atlas.
Latest from prompt/power
- Can an AI chatbot be your therapist? Where the rules stand in the U.S., Canada and beyondNov 16
- ChatGPT, Claude, Gemini and Copilot: what every AI plan costs in CanadaNov 16
- Nvidia’s first earnings without Jensen Huang: the numbers to watch on TuesdayNov 16
- How much energy does one AI chat use? What Google, OpenAI and Mistral have actually disclosedNov 15
- Gemini glasses cost US$395 and up, but Canadians can’t buy themNov 15
Leave a Reply